Large beige industrial building with ventilation grilles, rooftop steam, surrounding shrubs, and a construction site under a blue sky

Upper Chesapeake Generator Upgrade & Tank Farm

A phased emergency power and gas infrastructure upgrade delivered across an active hospital campus with zero disruption to patient care.

Project Size
$6.3 Million
Location
Bel Air, MD
Owner
Univ. of Maryland Upper Chesapeake Health
Successful Coordinated Outages
Over 100
Subcontractors Managed
20 Plus
Industrial rooftop with large Messer liquid oxygen storage tanks, cooling equipment, and HVAC units.

Project Overview

Kimball served as the prime contractor for a complex, multi-phased infrastructure project at the University of Maryland Upper Chesapeake Health (UM UCH) campus in Bel Air, Maryland. UM UCH is the leading health care provider and second-largest private employer in Harford County, supporting over 3,500 staff and 650 physicians. The $6.3M project relocated the hospital's oxygen and nitrogen tank farm and constructed a new generator building to provide critical backup power for the entire campus, all while keeping hospital operations fully running throughout construction.

How We Delivered

Construction was executed in three tightly coordinated phases: relocating the existing tank farm, erecting the new generator building, and commissioning the new equipment. The generator building, a two-story, 1,800 sq. ft. pre-manufactured structure housing two 2,000 kW generators and associated motor control systems, was built on a constrained site adjacent to the facility's main loading dock, requiring close coordination with hospital operations to avoid disrupting medical deliveries.

Kimball managed more than 20 subcontractors across the project, planning over 100 scheduled power outages months in advance with hospital departments and other ongoing campus projects to maintain full continuity of care throughout construction. Cranes were used to set the generators, place oxygen tanks, and lift steel for the building, all coordinated around active patient access and medical deliveries. When a framing issue arose involving insulated wall panels, the team resolved it with an alternate vertical framing approach that preserved the building's architectural and structural integrity.

Close-up of tall industrial metal HVAC cooling towers with vertical fins against a clear blue sky

Scope of Work

Power Generation

✔ Installed two (2) 2,000 kW generators and associated motor control/gear

✔ Constructed a two-story, 1,800 sq. ft. pre-manufactured generator building

Gas & Utility Infrastructure

✔ Relocated and rebuilt the hospital's oxygen and nitrogen tank farm

✔ Installed a 100-foot-long, 10-foot-deep, 12-foot-wide underground duct bank with 55 4" conduits connecting new generators to the central utility plant and existing campus systems

✔ Fuel oil tank installation

Electrical & Mechanical

✔ Electrical distribution equipment upgrades

✔ Mechanical system upgrades to support the new generator building

Site & Operations

✔ Crane logistics for generator, tank, and steel placement coordinated around active loading dock and patient access

✔ Coordination of 100+ scheduled power outages with hospital departments and concurrent campus projects

✔ Phase 3 equipment commissioning

Aerial view of a commercial building rooftop with HVAC equipment, steam vents, and ongoing construction.

Key Challenges

✔ Delivering major power and gas infrastructure work without disrupting hospital operations or patient care

✔ Building on a constrained site directly adjacent to an active loading dock

✔ Coordinating crane lifts and equipment placement around medical deliveries and patient access

✔ Managing 20+ subcontractors across a sensitive, high-stakes healthcare environment

✔ Resolving a wall panel framing conflict without compromising the building's structural integrity

Outcomes

✔ Zero operational disruption to hospital departments throughout construction

✔ Successful integration of mission-critical power and gas systems into an active medical campus

✔ On-time delivery despite constrained site conditions and complex phasing

Large Messer liquid oxygen storage tanks on an industrial rooftop, marked with no-smoking and oxygen safety warnings.