McCormick Hunt Valley Plant
Locker Room Upgrade

Locker rooms for more than 900 employees rebuilt inside a live food manufacturing plant without disrupting production.

Project Size
$2.2 Million
Location
McCormick & Co., Hunt Valley, MD
Owner
McCormick & Co., Inc.
Completed
June 2020
Plant Status during construction
Fully Operational

Project Overview

McCormick's Hunt Valley headquarters needed its outdated men's and women's locker rooms modernized for more than 900 employees, and the plant had to keep producing throughout. Kimball served as prime contractor for the phased demolition and renovation.

How We Delivered

Kimball relocated materials and personnel, then worked in carefully sequenced phases so the plant stayed fully operational. On-site supervision and daily coordination kept subcontractors working safely and cleanly.

Scope of Work

Demolition & Structure

  • Performed selective demolition of the existing locker areas

  • Fabricated and installed a new mezzanine to make better use of the space

Locker Room Build-Out

  • Installed partitions, toilet and bath accessories, and ceramic tile flooring and walls

  • Installed carpeting and ceilings

  • Installed HVAC systems and thermal and moisture protection

  • Built secure, badged-access entry points

Key Challenges

  • Working inside an active food production environment with strict contamination controls

  • Receiving deliveries through limited, tightly controlled access

  • Keeping construction debris out of sensitive processing zones

Outcomes

  • Delivered upgraded locker facilities for more than 900 employees

  • Kept production running with zero operational impact

  • Completed the project on time