McCormick Hunt Valley Plant
Locker Room Upgrade
Locker rooms for more than 900 employees rebuilt inside a live food manufacturing plant without disrupting production.
Project Overview
McCormick's Hunt Valley headquarters needed its outdated men's and women's locker rooms modernized for more than 900 employees, and the plant had to keep producing throughout. Kimball served as prime contractor for the phased demolition and renovation.
How We Delivered
Kimball relocated materials and personnel, then worked in carefully sequenced phases so the plant stayed fully operational. On-site supervision and daily coordination kept subcontractors working safely and cleanly.
Scope of Work
Demolition & Structure
Performed selective demolition of the existing locker areas
Fabricated and installed a new mezzanine to make better use of the space
Locker Room Build-Out
Installed partitions, toilet and bath accessories, and ceramic tile flooring and walls
Installed carpeting and ceilings
Installed HVAC systems and thermal and moisture protection
Built secure, badged-access entry points
Key Challenges
Working inside an active food production environment with strict contamination controls
Receiving deliveries through limited, tightly controlled access
Keeping construction debris out of sensitive processing zones
Outcomes
Delivered upgraded locker facilities for more than 900 employees
Kept production running with zero operational impact
Completed the project on time