Keys Energy Center
Eighty-five thousand square feet of power plant buildings erected around turbines and generators that were already in place.
Project Overview
SNC-Lavalin Power selected Kimball as design-build contractor and prime general contractor for the vertical construction of the main Power Building and four support structures at the Keys Energy Center combined cycle power plant. Most contractors build the building first. Here the turbines and generators were already installed, and the buildings had to go up around them.
How We Delivered
Kimball developed a protection plan that encased each unit in timber framing and plywood, then sequenced construction so work moved ahead without damaging or disrupting the equipment. Crane and manlift operations, daily safety meetings, and a phased schedule kept the structure aligned with the mechanical and electrical work going on around it.
Scope of Work
Power Building
Erected a 52,000 sq. ft. pre-engineered metal Power Building over two natural gas turbines, two electric generators, and a steam turbine
Installed a 125-ton bridge crane and associated systems
Support Buildings
Built two electrical buildings
Built a warehouse with a mezzanine and a five-ton crane
Built an administrative building
Built a condensate polishing building beneath pre-installed cooling towers
Key Challenges
Building around installed turbines and generators that could not be damaged
Working beside a 450-foot pipe rack that left only 30 inches of clearance
Staging overlapping trades through limited access points in a high-security plant
Outcomes
Delivered more than 85,000 sq. ft. of facilities without damaging any installed equipment
Cut the impact of the pipe rack clearance by more than 30 percent by replacing cranes and manlifts with swing scaffolding and re-sequencing the schedule
Earned formal recognition from SNC-Lavalin for proactive problem-solving and coordination

