New statewide food distribution hub delivered for the State of Delaware, from site preparation through final occupancy.

Project Size
$17.5 Million
Location
Smyrna, DE
Owner
State of Delaware, Office of Management and Budget
Completed
June 2026
Warehouse Size
28,800 Sq Ft
Large gray industrial warehouse with multiple loading dock doors under a bright blue sky

Project Overview

The State of Delaware needed a modern hub for its Food Distribution Program, which supplies food to schools, TEFAP agencies, and senior centers statewide. Kimball served as general contractor for the new 28,800 sq. ft. warehouse in Smyrna, which holds frozen, refrigerated, and dry goods under one roof and replaces an aging facility at Fort DuPont.

How We Delivered

Soil conditions called for a surcharge program, so Kimball placed fill over the building pad and tracked settlement with monitoring plates before starting foundations. More than 40 subcontractors and suppliers worked under the State's badging and drug-testing requirements.

Modern industrial control room with a wood U-shaped desk, office chairs, and windows overlooking a manufacturing facility

Scope of Work

Building & Systems

  • Built a one-story, high-bay pre-engineered metal building on cast-in-place foundations

  • Installed freezer, refrigerated, and dry storage areas with pallet racks and dock levelers

  • Installed refrigeration, HVAC, and fire protection with an independent pump house and water storage tank

  • Installed an emergency generator, fire alarm, and video surveillance and security systems

Site Work

  • Regraded the site and installed paving, fencing, gates, and truck and car parking

  • Installed a sanitary force main with grinder pumps, a new waterline, and a fire water line

  • Built two stormwater management facilities and a new entrance onto South DuPont Parkway

Large warehouse interior with empty blue-and-yellow industrial storage racks and shelving

Key Challenges

  • Building on soils that needed preloading before foundations could start

  • Permitting and building a new highway entrance under a DelDOT permit

  • Meeting State badging and drug-testing requirements across the workforce

Outcomes

  • Delivered a ground-up, specialized storage facility for a public owner

  • Replaced aging infrastructure with a central location for delivering food to schools statewide

  • Built a hub that will accept nearly 5 million pounds of food a year, more than 3 million meals.