Four phases of locker room and tank alley upgrades built around production shifts at an ice cream manufacturing plant
Project Overview
Dreyer's Ice Cream plant in Laurel, Maryland needed its locker room facilities renovated and expanded while production continued. Kimball was general contractor for a project that began as a five-month job and grew when the owner directed added scope.
How We Delivered
Kimball sequenced the work in four phases around production shifts and the tank alley's operating schedule, enforcing dust and air quality controls throughout. Real-time walkthroughs and rolling approvals meant the project closed out without a final punch list.
Scope of Work
Phase 1: Maintenance Relocation
Demolished the existing maintenance spaces
Built a new mezzanine to house maintenance operations
Phase 2: New Locker Room
Built a new locker room in the former maintenance area, with partitions and MEP upgrades
Installed a rooftop HVAC unit for improved climate control
Phase 3: Existing Locker Rooms
Renovated the existing locker rooms one room at a time so lockers stayed available
Reconfigured wall layouts, flooring, plumbing, lighting, and finishes
Phase 4: Tank Alley
Installed wash basins, plumbing systems, backfill, and new flooring
Added a pedestrian door to improve worker safety and flow
Key Challenges
Working around production shifts and food safety regulations
Scheduling around operations in the tank alley
Controlling dust and air quality in an active food plant
Keeping locker rooms available while each one was renovated
Outcomes
Delivered modernized, expanded locker facilities for plant employees
Closed out without a final punch list
Finished under budget without disrupting plant operations