ATRF Data Center
Expansion
Electrical and infrastructure expansion inside a live data center with no impact to its operations.
Project Overview
The Frederick National Laboratory for Cancer Research needed more capacity in its data center at the Advanced Technology Research Facility, and the data center had to keep running while the work was done. Leidos Biomedical Research selected Kimball as prime contractor for the expansion in Frederick, Maryland.
How We Delivered
Early in the job, Kimball ran an exploratory switchgear outage, which showed the team the exact bracket and materials needed so the construction outages that followed were fully prepared. Kimball then proposed a revised outage schedule that eliminated the planned temporary chillers and generators.
Scope of Work
Electrical Infrastructure
Installed two UPS switchboards and new panelboards
Installed six power distribution units and coolant distribution units
Installed cable tray, conduit, feeders, and breakers to serve the new equipment
Controls & Closeout
Tied the new equipment into the building automation system
Tested, balanced, and commissioned the systems with Leidos
Added a card reader and cabling to upgrade the data center's access security
Key Challenges
Managing outages as the main project risk
Working in the same room as operating equipment, at times directly above it
Phasing electrical, mechanical, and low-voltage work inside a live, mission-critical facility
Outcomes
Eliminated temporary chillers and generators and returned a credit to the client
Gave Leidos downtime to carry out preventative maintenance
Completed the project with no impact to the building's data operations