ATRF Data Center
Expansion

Electrical and infrastructure expansion inside a live data center with no impact to its operations.

Project Size
$4.1 Million
Location
Frederick, MD
Owner
National Cancer Institute / Leidos Biomedical Research
Completed
July 2025
Impact to Data Operations
None

Project Overview

The Frederick National Laboratory for Cancer Research needed more capacity in its data center at the Advanced Technology Research Facility, and the data center had to keep running while the work was done. Leidos Biomedical Research selected Kimball as prime contractor for the expansion in Frederick, Maryland.

How We Delivered

Early in the job, Kimball ran an exploratory switchgear outage, which showed the team the exact bracket and materials needed so the construction outages that followed were fully prepared. Kimball then proposed a revised outage schedule that eliminated the planned temporary chillers and generators.

Scope of Work

Electrical Infrastructure

  • Installed two UPS switchboards and new panelboards

  • Installed six power distribution units and coolant distribution units

  • Installed cable tray, conduit, feeders, and breakers to serve the new equipment

Controls & Closeout

  • Tied the new equipment into the building automation system

  • Tested, balanced, and commissioned the systems with Leidos

  • Added a card reader and cabling to upgrade the data center's access security

Key Challenges

  • Managing outages as the main project risk

  • Working in the same room as operating equipment, at times directly above it

  • Phasing electrical, mechanical, and low-voltage work inside a live, mission-critical facility

Outcomes

  • Eliminated temporary chillers and generators and returned a credit to the client

  • Gave Leidos downtime to carry out preventative maintenance

  • Completed the project with no impact to the building's data operations