Railroad tracks leading to an industrial maintenance building with workers and yellow safety barriers

Amtrak Ivy City Yard
North Storage Track Expansion

Storage track expansion built inside an active rail yard without interrupting train movements.

Project Size
$9.9 Million
Location
Washington Terminal Yard, Washington, DC
Owner
National Railroad Passenger Corp. (Amtrak)
Completed
July 2021
Power Cutover
Zero Disruptions
Railway construction site with workers in safety gear, overhead electrical lines, tracks, and orange safety fencing

Project Overview

Kimball served as prime contractor for the Ivy City North Storage Facility at Amtrak's Washington Terminal Yard in D.C., a project critical to Tier III High-Speed Rail operations and the Acela fleet.

How We Delivered

Construction took place in tightly sequenced phases, with daily coordination with Amtrak Force Account personnel, a rail monitoring system, and carefully planned drilling to protect active rail lines. Kimball's in-house team managed safety, quality control, and scheduling, timing outages and work sequences to match Amtrak's operations.

Rail construction workers operating excavators beside an Amtrak locomotive on active railroad tracks

Scope of Work

Foundations & Structures

  • Installed 21 catenary pole foundations, plus foundations for guy anchors

  • Installed caissons with a rail monitoring system and carefully planned drilling, without affecting active rail lines

  • Built a conduit bridge with concrete foundations, attached to the service annex

  • Installed five light towers with foundations and high mast lighting

Utilities & Power

  • Installed concrete-encased duct banks and handholes

  • Installed new commissary switchgear and transformer with a grounding grid

  • Temporarily rerouted power to the service annex and commissary, then removed the existing transformer and energized the upgraded system

Drainage & Site

  • Installed 302 LF of 18-inch and 40 LF of 24-inch storm sewer, with a manhole, catch basins, and an industrial waste water sand chamber

  • Installed 1,118 LF of fencing with grounding

  • Fabricated the catenary steel structures and delivered them for Amtrak forces to erect

  • Built an industrial wastewater pump station with a valve chamber, control panels, and alarms, plus a new air compressor station

  • "Poured concrete equipment pads and pavement and installed bollards

Railroad workers in high-visibility gear repair tracks beside a rail-mounted excavator and maintenance train.

Key Challenges

  • Working under strict access restrictions and constant rail traffic

  • Keeping the service annex and commissary operating during the power cutover

  • Installing foundations next to active rail lines

Outcomes

  • Energized the upgraded power system without service disruption

  • Installed all new foundations without affecting active rail lines